Day 29

Thursday, June 11, 1998
 
 Today the Plumber, Electrician, Carpet Guy, among others will be here.  The plumber says he'll likely have his rough plumbing all done (wow!)  The heating guy is almost done with his rough-in stuff.
 
The windows will be going in today, almost all of them are here.  The doors won't be here until Tuesday.
 
 You could say they are ROCKIN' and ROLLIN' on getting things accomplished!!!
 
 If you haven't looked at the plans... go here:  PLANS
We've begun buying tile and have our carpet picked out:  INTERIOR
 
Or see another day's activities:
Day One - May 12
Day Two - May 13
Day Three - May 14
Day Four - May 15
Day Five - May 16
Day Six - May 17 - NOTHING (no work done)
Day Seven - May 18 - NO PHOTOS
Day Eight - May 19
Day Nine - May 20
Day Ten - May 21
Day Eleven - May 22
Day Twelve - May 23
(May 24-25th Vacation - days won't count)
Day Thirteen - May 26th -& Day Fourteen - May 27th NO PHOTOS
Day Fifteen - May 28th
Day Sixteen - May 29th
Day Seventeen - May 30th
Day Eighteen - May 31st
Day Nineteen - June 1st
Day Twenty - June 2nd
Day Twenty One - June 3rd
Day Twenty Two - June 4th
Day Twenty Three - June 5th
Day Twenty Four - June 6th
Day Twenty Five - June 7th
Day Twenty Six - June 8th
Day Twenty Seven - June 9th
Day Twenty Eight - June 10th
Day Twenty Nine - June 11th - News/No Photos